Client
Project Duration
Rigid Ireland
3 Weeks
Project Description
Construction of extensions, fit out and upgrade and civil works to rigid containers factory in Galvone Limerick.
Work Included
-
Construction of extension 100m2 to the current factory unit.
-
2 new steel frame extension adjoining the current factory.
-
Both extensions included piling, ground works, structural steel works, in-situ concrete works, installation of precast mezzanine floors & stairs.
-
All joinery, mechanical and electrical works were included.
-
Ground floor units fitted out with additional office units.
-
Installation of industrial petrol bypass separators, industrial grease trap and a new yard.