top of page
Unit E5 Eastway Business Park
Limerick, Ireland
Sat/Sun Closed
Mon - Fri 8.00 - 17.00
Client
Board of Management Our Ladys Abbey Adare.
Project Duration
Project Description
This project consisted of the construction of a new 96m2 classroom and joining lobby extending from the existing school.
9 Months
Work Included
-
Site setup and clear out before the foundations could be dug and poured.
-
The school was finished in split Roadstone Forticrete blockwork.
-
The gables at either end of the classroom reached a finish height of 9m with a 50° slope. These were all to match the existing school.
-
Solar panels were installed on the south facing roof.
-
The classroom was finished with grey non-slip flooring for child safety.
-
Velux windows were installed for natural light.
Civil Engineering
PHOTO-2022-08-30-17-13-46 g
PHOTO-2022-08-30-17-13-46 b
Civil Engineering
1/4
bottom of page