Client
Board of Management Our Ladys Abbey Adare.
Project Duration
9 Months
Project Description
This project consisted of the construction of a new 96m2 classroom and joining lobby extending from the existing school.
Work Included
-
Site setup and clear out before the foundations could be dug and poured.
-
The school was finished in split Roadstone Forticrete blockwork.
-
The gables at either end of the classroom reached a finish height of 9m with a 50° slope. These were all to match the existing school.
-
Solar panels were installed on the south facing roof.
-
The classroom was finished with grey non-slip flooring for child safety.
-
Velux windows were installed for natural light.